AIr Quality fails to meet health standards

The air quality in Chalmette, Lousiana failed to meet health standards on 12_23_2012 for both sulfur dioxide and hydrogen sulfide.

Air quality samples taken at DEQ's air monitor at Bluebird Park in Chalmette Vista, along the ExxonMobil  --  Rain CII corridor had sulfur dioxide readings as high as 216 parts per billion (ppb), 193 ppb, and 184 ppb.  This is way over the sulfur health standard of 75 ppb.

For hydrogen sulfide, the health standard of 30 parts per billion was measured at Valero Energy Meraux refinery's air monitor, with readings as high as 30 ppb, 12 ppb and 11 ppb.  Further east, at Joe Davies Elementary school, another DEQ air monitor had hydrogen sulfide readings as high as 27 ppb, 20 ppb, and 17 ppb. 

The 30 ppb hydrogen sulfide health limit is a standard in the State of California; the State of Louisiana has no such standard.................

Sunday, December 23, 2012

Chalmette Home Buyers


Potential home buyers can check various Quality of Life and other indexes for Chalmette, LA

Home Facts Community Information



Air Quality on a scale of 1 to 10  >>>>   2.9

Details day by day


Home Facts details State by State to check facts before you purchase a home

Saturday, December 22, 2012

air quality report December 2012




Based on the Louisiana Department of Environmental Quality (DEQ)’s and Valero Energy’s 2012 air monitor readings   , one would say the air quality in St. Bernard Parish is considerably poor.  It fails to meet current standards for sulfur dioxide (SO2), hydrogen sulfide (H2S), and particulate matter pollution (PM2.5 and PM10), and is likely to exceed protective screening levels.  Monitoring is a valuable tool to measure offsite effects from major sources.  More stringent pollution controls and enforcement of existing regulations is still needed to protect public health.
 

On December 21, 2012 the Algiers to Chalmette Ferry turned around due to a suspicion of a chemical release from the ExxonMobil and Rain CII Carbon industrial area in Chalmette Vista, according to  WWL TV News and           The Times Picayune .

DEQ has an air monitor in the Chalmette Vista neighborhood.  If the wind direction last night was towards the ferry, the "Ch_Vista" air monitor would not pickup those levels, as the air monitor is in the opposite direction. DEQ used to monitor the air on the west bank side of the Mississippi River, but dismantled the monitor after Hurricane Gustav in 2008.  Currently, there are three community monitors in St Bernard Parish.

Over the years, on-site monitors at ExxonMobil's oil refinery in Chalmette have shown the effects from the adjacent Rain CII Carbon petroleum coke plant. In a report to DEQ, ExxonMobil's monitored concentrations were reported above the occupational exposure limit of 0.5 parts per million (ppm) or 500 parts per billion (ppb) during 2011 and 2012, in DEQ document 8364090 .  The health standard for ambient air is 0.075 ppm or 75 ppb sulfur dioxide.


Pollution levels in Chalmette Vista fail to meet the health standards for sulfur dioxide (75 parts per billion) and particluate matter sized 2.5 micrometers or PM2.5 (35 ug/m3).  In Chalmette Vista, some of the higher readings this year for sulfur dioxide have been 229.3 ppb, 164.4ppb, and 138.5 ppb [well above 75 ppb].    At the Valero Energy monitor, the highest reading was 120 ppb SO2 and at the Meraux monitor was 59 ppb. 

In December alone high readings for SO2 at "Ch_Vista" were 108 ppb and 143 ppb (both on Dec 9th) and 241 ppb and 184 ppb (both on Dec 10th). For PM2.5 for the year, high readings have been 88 ug/m3 and 67 ug/m3[ well above 35 ug/m3]. This does NOT include data from January's marsh fire. Yet, variances and emission increases continue to be issued in St. Bernard Parish by DEQ without requiring updated pollution controls.

When sulfur dioxide combines with particulate matter, it alters the lung defenses and causes breathing problems, wheezing, chest tightness, and shortness of breath. It can lead to premature death.

Hydrogen sulfide levels have been high as well. Exposure to lower concentrations of hydrogen sulfide causes eye irritation, sore throat, cough, nausea, shortness of breath, and fluid in the lungs. Long-term, low-level exposure causes fatigue, loss of appetite, headaches, poor memory, dizziness, loss of teeth and anemia. It affects the nervous system and cellular respiration.

Residents of St. Bernard Parish are frequently exposed to hydrogen sulfide readings that fail to meet the EPA recommend daily exposure limit of 1.4 ppb (0.0014 ppm). EPA’s intermediate exposure level to this poisonous gas is 20 ppb; the acute exposure level is 70 ppb. The State of California health limit for hydrogen sulfide is 30 ppb; Louisiana has no such limit.

For the year 2012, some of the higher hydrogen sulfide readings at Ch_Vista were 62 ppb, 53 ppb, and 49 ppb.  Valero Energy's monitor's highest reading for 2012 was 78 ppb.  The highest reading at DEQ's Meraux monitor was 40 ppb.

In December 2012 alone, the DEQ's monitor in Chalmette Vista had high readings of hydrogen sulfide at 18 ppb (Dec 9th), 21 ppb (Dec 16th), and 29 ppb (Dec 10th & Dec 17th).

This Chamlette Vista  monitor is located at a neighborhood playground. DEQ does not issue community alerts when pollution levels are high.  The only time DEQ issued community alerts for air quality in St Bernard Parish was in the January marsh fire or for Ozone Action Days, when ground level ozone was expected to cause health concerns.

.

Friday, November 16, 2012

Power Outages at Valero Energy


2012 power outages

 

Valero's Meraux refinery has reported several power outages in 2012 that resulted in emergency flaring releases to-date of over 23,000 pounds of sulfur dioxide over the permitted amounts.

On May 2, 2012, although Valero reported a release of only 2,100 pounds of sulfur dioxide, Valero's air monitor on Ventura Drive in Chalmette measured sulfur dioxide levels in the neighborhood's air at 120 parts per billion SO2, well over the EPA sulfur health standard of 75 ppb SO2. No alerts were sent forth to residents.

Incident 139318 EDMS 8431647

In the July 21, 2012 startup from a downed electrical transformer, Valero's air monitor on Ventura Drive measured hydrogen sulfide at 78 ppb H2S. Valero has reported an estimated pollution release of 1,830 pounds SO2 and 19 pounds hydrogen sulfide. Louisiana doesnot have a health standard for hydrogen sulfide; the State of California limits air quality to 30 ppb H2S.Incident 141430 EDMS 8482465

 

 

April 10, 2012 Valero reported a faulty transfer switch at the power company's substation resulted in total refinery-wide power interruption. The refinery lost all power, didnot have radios or telephones to communicate and had only emergency backup lights. The "emergency" pollution releases continued for over 94 hours . Valero's initial sulfur emission estimates of 4,000 pounds were later revised to 15,199 pounds SO2 and 135 pounds hydrogen sulfide.  The DEQ 'Meraux' Site monitor measured sulfur dioxide levels at 21 ppb.   Incident 138647 EDMS 8469365

( Initial estimate EDMS 8459094 )

April 2, 2012 Valero reported a lightning strike tripped the charge pump on the hydrocracker unit, causing the safety shutdown of the unit and subsequent startup. Estimated pollution releases were reported as: 4,500 pounds sulfur dioxide and 49 pounds of hydrogen sulfide. Incident 13850 EDMS 8424052

 

Link to Valero's Ventura Drive monitor: http://lena.providenceeng.com/hourly.aspx
Link to DEQ's Site Data monitors, select "Meraux"  http://www.deq.louisiana.gov/portal/DIVISIONS/Assessment/AirFieldServices/AmbientAirMonitoringProgram/AirMonitoringData.aspx

 

Link to Valero's Ventura Drive air toxin sample results http://lena.providenceeng.com/Documents.aspx

 

Monday, November 12, 2012

Monday, November 5, 2012

So, I would tell everyone in NY and NJ to keep the faith.




"We are holding you up in prayer in your darkest moments. We have walked in your shoes. Keep your chin up. Take it day by day. And, don’t ever forget NOLA loves y’all!”
The photos are moving and the project is ongoing. Here are some of those that have been collected so far:

 



Believe in your neighborhood!
From Heather:

“I am a 5th generation New Orleanian. My family has weathered many floods and even yellow fever. But, Katrina took every ounce of strength for us to rebuild. I was living back at my child hood home at the time the storm hit trying to get my fledging business off the ground. It is located in Metairie, a suburb about 20 minutes outside of New Orleans. My parent’s home was flooded with over a foot of water from Katrina. I ended up being evacuated to Tulsa, Oklahoma to stay with my sister’s family. One of my dogs that had evacuated with me died in Oklahoma within a week of the hurricane hitting. It was a devastating loss which still lives with me today. I cried tears so hard while evacuated that sometimes I couldn’t breathe. And, a deep depression settled over me until I was able to return home. My business is my very own love letter to New Orleans. It is based upon my NOLA photography. So, I knew my body of work was more relevant than ever after Katrina. I had to get back HOME. I was gone from my beloved New Orleans for over 3 months. When I returned it was encouragement from friends, family and customers that held me together emotionally. And, my photography became my Post Katrina therapy. So, I would tell everyone in NY and NJ to keep the faith. Try to be patient with yourself and those around you. Please remember your recovery is not a sprint. It’s a marathon. Change will not come overnight. Be ready for twists and turns as the recovery unfolds. And, if you need to talk to someone, do it! Don’t bottle your emotions up. If you want to fall to your knees and cry, do it! Your loss is palpable and it’s okay to cry your eyes out till they are red and bloodshot. Not only does your neighborhood have to recover, YOU will have to heal from this tragic loss. Lastly, remember this: When you think the nation has moved on in the days of 24 hour cable news, think again. New Orleans intimately knows your pain and we are thinking of each of you in the long term. We are holding you up in prayer in your darkest moments. We have walked in your shoes. Keep your chin up. Take it day by day. And, don’t ever forget NOLA loves y’all!”
Photo courtesy of Heather


 

Thursday, November 1, 2012

October Air Quality St Bernard Parish

The EPA recommended daily exposure to hydrogen sulfide (H2S) is 1.4 parts per billion (ppb) (0.0014 ppm)  and was exceeded throughout the month.…..inhaling more than this concentration on a daily basis poses an appreciable risk of deleterious effects.
http://www.epa.gov/iris/toxreviews/0061tr.pdf . "Exposure to lower concentrations can result in eye irritation, a sore throat and cough, nausea, shortness of breath, and fluid in the lungs." "Long-term, low-level exposure may result in fatigue, loss of appetite, headaches, irritability, poor memory, and dizziness."

The State of California air quality standard limits ambient levels of hydrogen sulfide to 30 ppb H2S. The State of Louisiana has does not have such a standard. Hydrogen sulfide levels in Chalmette Vista exceeded 30 ppb H2S in October 2012, with the highest reading at 53 ppb H2S. 

Other States have lower hydrogen sulfide air quality limits.
Other states

The EPA health standard for sulfur dioxide is 75 ppb SO2. The Louisiana DEQ has stated Sulfur Dioxide (SO2) at the 12 ppb SO2 level triggers headaches and other adverse effects.

The health standard for fine particulate matter (PM2.5) is 35 ug/m3. This standard was exceeded already in October 2012, according to the three community monitors.
Air Quality in October in St Bernard Parish


 

St Bernard Parish three ambient air monitors shown above

Above graph of location of the three community ambient air monitors along with the former monitor locations on the west bank of the river and the local High School.  The former locations were used for a LDEQ air quality study when the sulfur limit was 140 ppb SO2.  Now it is 75 ppb SO2.


In addition to the three community monitors, other air sample results are available at the Valero Ventura Drive site, under documents .  Some of these Valero air sample results are linked below.
Some refineries post real-time fenceline data, like here at a Phillips refinery.  Notice the larger "green belt" buffer in the photo.  

Valero Ventura Drive Sample date -- analyzed date

10/07/2012 sample analyzed 10/12/2012
http://lena.providenceeng.com/Reports/CAMs%20Lab%20Data%2010-7-12.pdf
10/01/2012 sample analyzed 10/11/2012
http://lena.providenceeng.com/Reports/CAMs%20Lab%20Data%2010-1-12.pdf
9/25/2012 sample analyzed 10/3/2012
http://lena.providenceeng.com/Reports/CAMs%20Lab%20Data%209-25-12.pdf
9/19/2012 sample analyzed 9/24/2012
http://lena.providenceeng.com/Reports/CAMs%20Lab%20Data%209-19-12.pdf
9/13/2012 sample analyzed 9/20/2012
http://lena.providenceeng.com/Reports/CAMs%20Lab%20Data%209-13-12.pdf
9/07/2012 sample analyzed 9/18/2012
http://lena.providenceeng.com/Reports/CAMs%20Lab%20Data%209-7-12.pdf
9/01/2012 sample analyzed 9/13/2012
http://lena.providenceeng.com/Reports/CAMs%20Lab%20Data%209-1-12.pdf

Excess emissions 2012 2nd Quarter

Excess emissions 2012 1st Quarter

Wednesday, October 31, 2012

October air quality readings

  
October 2012
Air Quality Readings
St. Bernard Parish
Hydrogen Sulfide
and Sulfur Dioxide
health standards
SO2   75 ppb
H2S    1.4 ppb EPA recommended daily 
PM2.5   35
 
10/1/2012 midnight Ch_Vista 4 ppb H2S
1am Ch_Vista 4 ppb H2S
2am Ch_Vista 4 ppb H2S
3am Ch_Vista 4 ppb H2S
4am Ch_Vista 3 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 4 ppb H2S
7am Ch_Vista 4 ppb H2S
8am Ch_Vista 4 ppb H2S
Meraux SO2 8.8ppb
9am Ventura SO2 8ppb
10am Meraux SO2 8.6ppb
11am Ventura SO2 8ppb
10/2/2012 4am Ch_Vista 4 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 4 ppb H2S
Ch_Vista PM10  -60
7am Ch_Vista 4 ppb H2S
Ch_Vista PM10  -52
Ventura PM10  -49
8am Ch_Vista 4 ppb H2S
Ventura PM10  -49
  6pm Meraux 4 ppb H2S
7pm Ventura 6 ppb H2S
8pm Ventura PM10  -44
9pm Ventura 5 ppb H2S
  Meraux 5 ppb H2S
Meraux SO2 8.1ppb
10pm Ventura 7 ppb H2S
Ventura PM10  -45
Meraux 5 ppb H2S
11pm Ventura 8 ppb H2S
  Ventura PM10  -53
Meraux 4 ppb H2S
10/3/2012 midnight Ch_Vista 6 ppb H2S
Ventura 5 ppb H2S
Ventura PM10  -39
2am Ch_Vista 5 ppb H2S
3am Ch_Vista 5 ppb H2S
4am Ch_Vista 4 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 4 ppb H2S
7am Ch_Vista 4 ppb H2S
8am Ch_Vista 4 ppb H2S
Ch_Vista PM10  -41
5pm Ventura PM10  -41
8pm Ch_Vista 4 ppb H2S
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/4/2012 midnight  Ch_Vista 4 ppb H2S
1am Ch_Vista 4 ppb H2S
2am Ch_Vista 4 ppb H2S
3am Ch_Vista 4 ppb H2S
4am Ch_Vista 4 ppb H2S
6pm Ch_Vista 4 ppb H2S
7pm Ch_Vista 4 ppb H2S
8pm Ch_Vista 4 ppb H2S
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/5/2012 midnight Ch_Vista 4 ppb H2S
1am Ventura 9 ppb H2S
2am Ch_Vista 4 ppb H2S
Ventura 6 ppb H2S
3am Ch_Vista 5 ppb H2S
Ventura 6 ppb H2S
4am Ch_Vista 6 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 4 ppb H2S
Ventura 5 ppb H2S
7am Ch_Vista SO2 8.2 ppb
Ventura PM10 --42
6pm Ch_Vista 4 ppb H2S
7pm Ch_Vista 4 ppb H2S
8pm Ch_Vista 6 ppb H2S
9pm Ch_Vista 6 ppb H2S
10pm Ch_Vista 5 ppb H2S
11pm Ch_Vista 5 ppb H2S
Ventura 4 ppb H2S
10/6/2012 midnight Ch_Vista 5 ppb H2S
1am Ch_Vista 5 ppb H2S
Ventura 5 ppb H2S
2am Ch_Vista 7 ppb H2S
Ventura 4 ppb H2S
3am Ch_Vista 6 ppb H2S
4am Ch_Vista 6 ppb H2S
Ventura 4 ppb H2S
5am Ch_Vista 6 ppb H2S
Ventura 4 ppb H2S
6am Ch_Vista 5 ppb H2S
Ventura 4 ppb H2S
7am Ch_Vista 7 ppb H2S
Ch_Vista PM10 -52
Ch_Vista PM2.5 -27
Ventura PM10  -65
8am Ch_Vista 4 ppb H2S
Ventura PM10  -59
5pm Ch_Vista SO2 31.4 ppb
6pm Ch_Vista 5 ppb H2S
7pm Ch_Vista 4 ppb H2S
Ch_Vista PM2.5-30
8pm Ch_Vista 4 ppb H2S
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 5 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/7/2012 midnight Ch_Vista 4 ppb H2S
2am Ch_Vista 4 ppb H2S
3am Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/8/2012 midnight Ch_Vista 4 ppb H2S
4am Ch_Vista 4 ppb H2S
9am Ch_Vista 4 ppb H2S
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 5 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/9/2012 7pm Ventura PM10 -46
8pm Ch_Vista 5 ppb H2S
Ch_Vista PM2.5 26
Ventura PM10 -35
9pm Ch_Vista 6 ppb H2S
Ventura PM10 -40
10pm Ch_Vista 6 ppb H2S
Meraux 3 ppb H2S
11pm Ch_Vista 5 ppb H2S
Ventura 4 ppb H2S
Meraux 4 ppb H2S
10/10/2012 midnight Ch_Vista 6 ppb H2S
Ventura 4 ppb H2S
1am Ventura 5 ppb H2S
2am Ch_Vista 12 ppb H2S
Ventura 7 ppb H2S
3am Ch_Vista 9 ppb H2S
Ventura 7 ppb H2S
4am Ch_Vista 6 ppb H2S
Ventura 6 ppb H2S
5am Ch_Vista 7 ppb H2S
Ventura 6 ppb H2S
6am Ch_Vista 7 ppb H2S
Ch_Vista PM10 -33
Ventura 6 ppb H2S
7am Ch_Vista 5 ppb H2S
Ventura PM10-39
8am Ch_Vista 4 ppb H2S
  Ch_Vista PM10-36
9am Ch_Vista 4 ppb H2S
Ch_Vista PM10-37
5pm Ch_Vista PM10-58
7pm Ch_Vista 4 ppb H2S
Ventura 4 ppb H2S
8pm Ch_Vista 5 ppb H2S
Ventura 6 ppb H2S
9pm Ch_Vista 7 ppb H2S
Ventura 4 ppb H2S
10pm Ch_Vista 6 ppb H2S
Ventura 3 ppb H2S
11pm Ch_Vista 9 ppb H2S
Ventura 9 ppb H2S
10/11/2012 midnight Ch_Vista 10 ppb H2S
Ventura 12 ppb H2S
Meraux 7 ppb H2S
1am Ch_Vista 9 ppbH2S
Ventura 10 ppb H2S
Meraux 7 ppb H2S
2am Ch_Vista 11 ppbH2S
Ventura 9 ppbH2S
Meraux 7 ppb H2S
3am Ch_Vista 11ppbH2S
Ventura 10 ppb H2S
Meraux 6 ppb H2S
4am Ch_Vista 11ppbH2S
Ventura 10 ppb H2S
Meraux 5 ppb H2S
5am Ch_Vista 9 ppbH2S
Ventura 9 ppbH2S
Meraux 4 ppb H2S
6am Ch_Vista 5 ppb H2S
Ch_Vista PM2.5-34.8
Ventura 7 ppb H2S
7am Ch_Vista 4 ppb H2S
Ventura PM10 -43
Ch_Vista PM10-47
6pm Ventura PM10-47
7pm Ventura PM10-45
9pm Ch_Vista SO2 10.5 ppb
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/12/2012 midnight Ch_Vista 6 ppb H2S
Ventura 5 ppb H2S
1am Ventura 17 ppb H2S
Meraux 5 ppb H2S
2am Ch_Vista 9 ppb H2S
Ventura 14 ppb H2S
Meraux 5 ppb H2S
3am Ch_Vista 7 ppb H2S
Ventura 8 ppb H2S
4am Ch_Vista 6 ppb H2S
Ventura 6 ppb H2S
5am Ch_Vista 5 ppb H2S
Ch_Vista PM10-36
Ventura 4 ppb H2S
Meraux SO2 11.5 ppb
6am Ch_Vista 4 ppb H2S
7am Ventura PM10-46
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
10/13/2012 midnight Ch_Vista 4 ppb H2S
1am Ch_Vista 4 ppb H2S
2am Ch_Vista 4 ppb H2S
3am Ch_Vista 4 ppb H2S
4am Ch_Vista 4 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 4 ppb H2S
7am Ventura PM10-41
4pm Ch_Vista PM2.5-34.9
8pm Ch_Vista PM10-39
11pm Ventura PM10-36
10/14/2012 midnight Ch_Vista 19 ppb H2S
3am Ch_Vista 5 ppb H2S
4am Ch_Vista 6 ppb H2S
5am Ch_Vista 5 ppb H2S
6am Ch_Vista 5 ppb H2S
7am Ch_Vista 6 ppb H2S
  Ch_Vista SO2 5.2 ppb
8am Ch_Vista 4 ppb H2S
Meraux SO2 5.4 ppb
9am Ch_Vista 4 ppb H2S
5pm Ventura PM10-52
10pm Meraux SO2 7.3 ppb
10/15/2012 midnight Ch_Vista 4 ppb H2S
1am Ch_Vista 4 ppb H2S
Ventura 6 ppb H2S
2am Ch_Vista 4 ppb H2S
Ventura 4 ppb H2S
3am Ch_Vista 4 ppb H2S
4am Ch_Vista 4 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 4 ppb H2S
noon Ch_Vista PM2.5-36.6
10/16/2012 midnight Ch_Vista 4 ppb H2S
10am Ventura PM10-43
6pm Meraux SO2 9.4 ppb
9pm Ch_Vista 4 ppb H2S
Ch_Vista PM2.5-34.7
Ch_Vista PM10-44
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/17/2012 midnight Ch_Vista 4 ppb H2S
2am Ch_Vista 5 ppb H2S
3am Ch_Vista 5 ppb H2S
4am Ch_Vista 4 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 4 ppb H2S
7am Ch_Vista 4 ppb H2S
8am Ch_Vista 7 ppb H2S
9am Ch_Vista 6 ppb H2S
10am Ch_Vista 6 ppb H2S
Ventura PM10-51
11am Ch_Vista 5 ppb H2S
Ventura PM10-56
noon Ch_Vista 7 ppb H2S
  Ventura PM10-44
1pm Ch_Vista 7 ppb H2S
  Ventura PM10-56
2pm Ch_Vista 11 ppb H2S
  Ventura PM10-49
3pm Ch_Vista 10 ppb H2S
4pm Ch_Vista 7 ppb H2S
5pm Ch_Vista 7 ppb H2S
6pm Ch_Vista 6 ppb H2S
7pm Ch_Vista 7 ppb H2S
8pm Ch_Vista 7 ppb H2S
9pm Ch_Vista 11 ppb H2S
10pm Ch_Vista 11 ppb H2S
11pm Ch_Vista 7 ppb H2S
10/18/2012 midnight Ch_Vista 6 ppb H2S
1am Ch_Vista 5 ppb H2S
2am Ch_Vista 4 ppb H2S
3am Ch_Vista 4 ppb H2S
4am Ch_Vista 4 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 5 ppb H2S
Meraux SO2 7.2 ppb
7am Ch_Vista 4 ppb H2S
8am Ch_Vista 4 ppb H2S
4pm Ch_Vista 4 ppb H2S
5pm Ch_Vista 4 ppb H2S
6pm Ch_Vista 4 ppb H2S
7pm Ch_Vista 4 ppb H2S
8pm Ch_Vista 4 ppb H2S
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/19/2012 midnight Ch_Vista 4 ppb H2S
Meraux 6 ppb H2S
1am Meraux 6 ppb H2S
2am Ch_Vista 5 ppb H2S
3am Ch_Vista 4 ppb H2S
4am Ch_Vista 6 ppb H2S
5am Ch_Vista 5 ppb H2S
Ventura 4 ppb H2S
6am Ch_Vista 5 ppb H2S
Ventura 4 ppb H2S
Meraux 4 ppb H2S
7am Ventura 5 ppb H2S
8am Ch_Vista 4 ppb H2S
5pm Ch_Vista 4 ppb H2S
Ch_Vista PM10 -49
Ventura PM10-41
6pm Ch_Vista 4 ppb H2S
Ch_Vista PM10-49
Ventura PM10 -35
7pm Ch_Vista SO2 7.3ppb
Ch_Vista 4 ppb H2S
  Ch_Vista PM10- 44
Ventura PM10 -61
Meraux SO2 9.5 ppb
8pm Ch_Vista SO2 8.4ppb
  Ch_Vista 5 ppb H2S
Ch_Vista PM10-55
Ventura PM10 -54
Meraux SO2 10.9 ppb
9pm Ch_Vista 5 ppb H2S
  Ch_Vista PM10-42
Ventura SO2 7 ppb
Ventura 4 ppb H2S
  Ventura PM10-61
Meraux SO2 8.2 ppb
10pm Ch_Vista 5 ppb H2S
Ch_Vista PM10-54
Ventura 4 ppb H2S
Ventura PM10 -45
Meraux SO2 6.4 ppb
11pm Ch_Vista 5 ppb H2S
Ch_Vista PM10-37
Ventura 6 ppb H2S
Ventura PM10 -42
10/20/2012 midnight Ch_Vista 5 ppb H2S
  Ventura 5 ppb H2S
1am Ch_Vista 5 ppb H2S
Meraux SO2 6.9 ppb
2am Ch_Vista 5 ppb H2S
3am Ch_Vista 6 ppb H2S
Ventura PM10 -54
4am Ch_Vista 6 ppb H2S
Ventura PM10 -60
5am Ch_Vista 5 ppb H2S
Ventura 5 ppb H2S
6am Ch_Vista 6 ppb H2S
Ch_Vista PM10- 55
Ventura PM10 -55
7am Ch_Vista 6 ppb H2S
Ch_Vista PM10 -59
Ventura PM10 -69
Meraux SO2 6.8 ppb
8am Ch_Vista 4 ppb H2S
  Ch_Vista PM10 -51
  Ventura PM10 -71
9am Ch_Vista 4 ppb H2S
Ch_Vista PM10 -48
6pm Ch_Vista 6 ppb H2S
7pm Ch_Vista 30 ppb H2S
Ch_Vista SO2 7.8 ppb
Ch_Vista PM10 -48
  Ventura PM10-43
8pm Ch_Vista 14 ppb H2S
Ch_Vista SO2 9.6 ppb
Ventura 4 ppb H2S
  Ventura PM10 -52
9pm Ch_Vista 24 ppb H2S
Ch_Vista SO2 11.5 ppb
Ch_Vista PM2.5- 23
Ventura 5 ppb H2S
Ventura PM10 -59
Meraux SO2 7.1 ppb
10pm Ch_Vista 53 ppb H2S
Ch_Vista SO2 8.4 ppb
  Ch_Vista PM10 -44
Ventura 8 ppb H2S
Ventura PM10 -45
11pm Ch_Vista 43 ppb H2S
Ventura 10 ppb H2S
Ventura PM10 -46
10/21/2012 midnight Ch_Vista 28 ppb H2S
Ventura 10 ppb H2S
Ventura PM10  -35
Meraux  SO2 6.6 ppb
1am Ventura 8 ppb H2S
2am Ch_Vista 19 ppb H2S
Ventura 7 ppb H2S
Meraux  5 ppb H2S
3am Ch_Vista 12 ppb H2S
Ventura 6 ppb H2S
4am Ch_Vista 9 ppb H2S
Ventura 7 ppb H2S
5am Ch_Vista 7 ppb H2S
Ventura 5 ppb H2S
6am Ch_Vista 6 ppb H2S
Ventura 4 ppb H2S
7am Ch_Vista 5 ppb H2S
3pm Ventura PM10 -47
9pm Ventura PM10 -42
10pm Meraux  6 ppb H2S
11pm Meraux  6 ppb H2S
10/22/2012 midnight Ch_Vista 7 ppb H2S
Ventura 5 ppb H2S
Meraux 5 ppb H2S
1am Ch_Vista 7 ppb H2S
Ventura 5 ppb H2S
Meraux 4 ppb H2S
2am Ch_Vista 7 ppb H2S
Ventura 6 ppb H2S
3am Ch_Vista 7 ppb H2S
Ventura 4 ppb H2S
4am Ch_Vista 5 ppb H2S
5am Ch_Vista 4 ppb H2S
6am Ch_Vista 4 ppb H2S
7am Ch_Vista 4 ppb H2S
Ventura PM10 -53
6pm Ch_Vista 4 ppb H2S
7pm Ch_Vista 4 ppb H2S
8pm Ch_Vista 4 ppb H2S
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/23/2012 midnight Ch_Vista 4 ppb H2S
2am Ch_Vista 4 ppb H2S
Ventura PM10-55
3am Ch_Vista 4 ppb H2S
4am Ch_Vista 4 ppb H2S
Meraux 5 ppb H2S
5am Ch_Vista 6 ppb H2S
6am Ch_Vista 6 ppb H2S
7am Ch_Vista 4 ppb H2S
Ventura PM10-59
9pm Ch_Vista SO2 13.5 ppb 
10pm Ch_Vista SO2 13.5 ppb
10/24/2012 midnight Ch_Vista 20.6 ppb SO2
Ch_Vista 4 ppb H2S
2am Ch_Vista 5 ppb H2S
Ventura 6 ppb H2S
3am Ch_Vista 5 ppb H2S
4am Ch_Vista 5 ppb H2S
5am Ch_Vista 5 ppb H2S
6am Ch_Vista 5 ppb H2S
7am Ch_Vista 4 ppb H2S
6pm Ch_Vista 4 ppb H2S
7pm Ch_Vista 4 ppb H2S
8pm Ch_Vista 4 ppb H2S
  Ch_Vista SO2 20.8 ppb
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
Ch_Vista SO2 10.3 ppb
10/25/2012 midnight Ch_Vista 4 ppb H2S
1am Ch_Vista 4 ppb H2S
2am Ch_Vista 4 ppb H2S
3am Ch_Vista 4 ppb H2S
4am Ch_Vista 4 ppb H2S
Ventura 4 ppb H2S
5am Ch_Vista 5 ppb H2S
6am Ch_Vista 5 ppb H2S
7am Ch_Vista 4 ppb H2S
8am Ch_Vista 4 ppb H2S
5pm Ch_Vista 4 ppb H2S
6pm Ch_Vista 4 ppb H2S
7pm Ch_Vista 4 ppb H2S
8pm Ch_Vista 4 ppb H2S
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 4 ppb H2S
10/26/2012 midnight Ch_Vista 4 ppb H2S
1am Ventura 11 ppb H2S
2am Ch_Vista 8 ppb H2S
Ventura 11 ppb H2S
Meraux 15 ppb H2S
3am Ch_Vista 10 ppb H2S
Ventura 9 ppb H2S
Meraux 6 ppb H2S
4am Ch_Vista 11 ppb H2S
5am Ch_Vista 9 ppb H2S
6am Ch_Vista 5 ppb H2S
7am Ch_Vista 4 ppb H2S
4pm Ch_Vista 4 ppb H2S
5pm Ch_Vista 6 ppb H2S
Meraux 5 ppb H2S
6pm Ch_Vista 3 ppb H2S
Ventura PM10 -36
Meraux 5 ppb H2S
7pm Ch_Vista 4 ppb H2S
Meraux 4 ppb H2S
8pm Ch_Vista 3 ppb H2S
9pm Ch_Vista 4 ppb H2S
10pm Ch_Vista 4 ppb H2S
11pm Ch_Vista 5 ppb H2S
Ventura PM10-38
10/30/2012 1am Meraux 5 ppb H2S
  2am Meraux 5 ppb H2S
3am Ch_Vista 4 ppb H2S
Meraux 5 ppb H2S
4am Ch_Vista 6 ppb H2S
Meraux 8 ppb H2S
5am Ch_Vista 5 ppb H2S
Ventura 5 ppb H2S
Meraux 6 ppb H2S
6am Ch_Vista 6 ppb H2S
Ventura 6 ppb H2S
Meraux 4 ppb H2S
7am Ch_Vista 6 ppb H2S
Ch_Vista PM10- 34
Ventura 4 ppb H2S
6pm Ch_Vista 4 ppb H2S
Meraux 8 ppb H2S
Meraux SO2 16 ppb
7pm Ch_Vista 4 ppb H2S
Ch_Vista PM10 -40
Meraux SO2 27.2 ppb
8pm Ch_Vista 4 ppb H2S
Ventura 4 ppb H2S
Ventura PM10 -68
9pm Ch_Vista 4 ppb H2S
Meraux SO2 14.4 ppb
10pm Ch_Vista 4 ppb H2S
Meraux SO2 14.7 ppb
11pm Ch_Vista 4 ppb H2S
10/31/2012 midnight Ch_Vista 4 ppb H2S
Ventura 4 ppb H2S
Ventura SO2 21 ppb
    Meraux SO2 22.8 ppb
1am Ventura 6 ppb H2S
Ventura SO2 14 ppb
  Meraux SO2 11.9 ppb
2am Ch_Vista 5 ppb H2S
Ventura SO2 5 ppb
3am Ch_Vista 5 ppb H2S
4am Ch_Vista 5 ppb H2S
5am Ch_Vista 5 ppb H2S
6am Ch_Vista 6 ppb H2S
7am Ch_Vista 4 ppb H2S
Ventura 6 ppb H2S
8am Ch_Vista 5 ppb H2S
  Meraux SO2 59.1 ppb
9am Ch_Vista 4 ppb H2S
Ventura SO2 19 ppb
  Meraux SO2 19.8 ppb
10am Ch_Vista 4 ppb H2S
Ventura SO2 8 ppb
Meraux SO2 9 ppb
11am Ch_Vista 4 ppb H2S
Ventura SO2 6 ppb
  Ventura PM10 -46
  Meraux SO2 10.1 ppb
noon Ch_Vista 4 ppb H2S
Ventura SO2 9 ppb
1pm Ch_Vista 4 ppb H2S
Ventura SO2 7 ppb
2pm Ch_Vista 4 ppb H2S
Ventura SO2 5 ppb
3pm Ch_Vista 4 ppb H2S
4pm Ch_Vista 4 ppb H2S
Ventura SO2 8 ppb
5pm Ch_Vista 4 ppb H2S
6pm Ch_Vista 4 ppb H2S
7pm Ch_Vista 4 ppb H2S
8pm Ch_Vista 4 ppb H2S
9pm Ch_Vista 5 ppb H2S
Meraux SO2 10 ppb
 10pm Ch_Vista 6 ppb H2S
  Meraux SO2 12.7 ppb
11pm Ch_Vista 6 ppb H2S

Blog Archive